Fortress Transportation and Infrastructure Investors’ pursuit of the Long Ridge Energy Terminal combined-cycle gas turbine power plant project reached financial close on February 15, 2019.

The project involves the design, build, finance and operations of a 485 MW combined-cycle plant, which uses both a gas and a steam turbine to produce up to 50 percent more electricity from the same fuel than a traditional simple-cycle plant.

The project will be built in Monroe County, Ohio, USA, and will be one of the most energy efficient power plants of any type in the world. Multiple counter-parties have entered into long-term power purchase agreements with the project to secure the plant’s output.

Operis was pleased to perform a formal audit of the financial model to finance the development of the plant.

Share now

CONTACT US

Please get in touch with either of our regional offices.

https://www.operis.com/wp-content/uploads/2022/11/22_09_Chris_A-0376.jpg
Chris Aldred
Head of Advisory

+44 207 562 0433

[javascript protected email address]
https://www.operis.com/wp-content/uploads/2025/01/Operis_portrait-7555-1-scaled-500x500.jpg
James Jones
Director

+44 207 562 0492

[javascript protected email address]
https://www.operis.com/wp-content/uploads/2022/11/22_09_Holly-0555.jpg
Holly Eveleigh
Director

+44 20 7562 0457

[javascript protected email address]

Operis Europe

View Google Map
+44 207 562 0400
[javascript protected email address]

Operis North America

View Google Map
+1 647 846 7382
[javascript protected email address]

CONTACT US

Discuss your requirements with us

https://www.operis.com/wp-content/uploads/2022/11/22_09_Chris_A-0376.jpg
Chris Aldred
Head of Advisory

+44 207 562 0433

[javascript protected email address]
This field is for validation purposes and should be left unchanged.
Name(Required)